Centralized Tank Farm Assaluyeh Phase II
Key Specifications
Capacity & Configuration:
- Total Storage Capacity:5 million m³
 - Tank Sizes:50,000 to 120,000 m³ per tank
 - Product Types:
- Condensate (60%)
 - Naphtha (20%)
 - Gasoil (15%)
 - Specialty chemicals (5%)
 
 
Design Parameters:
- Design Standards:API 650, API 653
 - Operating Pressure:Atmospheric to 0.5 barg
 - Temperature Range:-10°C to 80°C
 - Corrosion Protection:Cathodic protection and advanced coatings
 
Project Details
Storage Technology:
- Floating Roof Tanksfor condensate and light crude
 - Fixed Roof Tankswith internal floating decks for refined products
 - Double-Wall Tanksfor environmental protection
 - Advanced Leak Detection Systems
 
Key Systems:
- Pipeline Integrationwith jetties and processing facilities
 - Vapor Recovery Units(VRU)
 - Fire Protection and Safety Systems
 - Automated Inventory Management
 
Operational Challenges
Product Contamination Control: Managing multiple products in shared infrastructure
VOC Emissions Control: Meeting stringent environmental regulations
Geotechnical Considerations: Soil stabilization in coastal area
Emergency Response: Large-scale spill containment and fire safety
Strategic Importance
- Enables export flexibilityfor South Pars condensate production
 - Provides strategic storagefor production optimization
 - Reduces shipping coststhrough larger vessel loading
 - Supports downstream petrochemical operations
 
Engineering Opportunities for Sabz Engineering Co.
Detailed Engineering:
- Tank foundation designfor challenging soil conditions
 - Pipeline stress analysisfor transfer systems
 - Structural designfor access platforms and piping supports
 
Software Solutions:
- Inventory Management Systemintegration
 - Leak Detection and Monitoring Software
 - Predictive Maintenancefor rotating equipment
 
Project Management:
- Modular constructionplanning
 - International procurementof specialized equipment
 - Commissioning and startupmanagement
 
Sustainability Features
Vapor Recovery: 98% VOC capture efficiency
Solar-powered monitoring systems
Advanced wastewater treatment
Spill prevention and containment systems
Project Economics
Parameter  | Value  | 
Investment  | $380 million  | 
Payback Period  | 5-6 years  | 
ROI  | 20-22%  | 
Operational Cost Savings  | 15% compared to scattered storage  | 
Technical Comparison: Phase I vs Phase II
Parameter  | Phase I  | Phase II  | 
Total Capacity  | 1.8 million m³  | 2.5 million m³  | 
Automation Level  | Basic  | Advanced DCS  | 
VOC Recovery  | 85%  | 98%  | 
Safety Systems  | Conventional  | SIL-2 Certified  | 
SEC Scope:
- Design + Material take-off + Fabrication Drawing Preparation for 12 Units Storage Tanks 30,000 Tons
 